GO Caterpillar Motor 3508

Project

Customer:

Slovnaft, a.s.

Project Completion Date:

2024

The repair involved the complete disassembly of the combustion engine, thorough cleaning of all components, and inspection of key parts—such as cylinder heads and connecting rods—using 3D measurement. The crankcase was repaired on a horizontal machining center, followed by the reassembly of engine components and a functional test. The entire repair process, from cleaning and measurement to machining, was carried out at Rudos.

The engine is now fully prepared for another 25,000 Mth of operation.